Sunday, May 6, 2018

Quants 1 - Time and Work

Key Points to Remember:

If A can do a piece of work in n days, then A's 1 day work is 1/n.
If A is thrice as good as B, then 
     (i) Ratio of work done by A to B is 3:1
     (ii) Ratio of time taken by A and B is 1:3

Practice Questions:

Question 1:
Mahi takes 3 hours to complete a task and Sonu takes 7 hours to complete the same task. If Mahi and Sonu work together, how long will they take to complete the same?

Mahi's 1 hour work = 1/3
Sonu's 1 hour work = 1/7
Mahi + Sonu 's 1 hour work = 1/3 + 1/7 = 10/21
Hence Mahi and Sonu take 21/10 hours to complete if they work together.
21/10 = 2 1/10 hours or 2.1 hours


Question 2:
Yuvi and Cheeku together can complete a piece of work in 8 days. If Yuvi alone can do the same in 24 days, how long will Cheeku take time to complete?

Yuvi + Cheeku's 1 day work = 1/8
Yuvi's 1 day work = 1/24
Cheeku's 1 day work = (1/8) - (1/24) = 2/24
Hence Cheeku takes 24/2 = 12 days to complete the work.


Question 3:
Ziva is twice as good as Gracia and together they finish the piece of work in 20 days. In how many days will Ziva alone do the work?

Ziva's work : Gracia's work = 2:1
Ziva + Gracia's 1 day work = 1/20
Dividing 1/20 in the ratio of 2:1
Ziva's work = (1/20) * 2/3 = 1/30
Hence Ziva takes 30 days to complete the work.

(Task for the readers, find the days for Gracia to complete the work)


Question 4:
Ram can do a certain job in 16 days. Sam is 60% more efficient than Ram. How many days does Sam alone take to complete the task?

Ratio of times taken by Ram and Sam = 160:100 = 8:5
If Sam takes x days to complete the task,
Then,
8 : 5 :: 16 : x => 8x = 80
Hence, Sam takes, 10 days to complete the task.


Question 5:
Sakshi can do 1/4th of the work in 10 days. Priyanka can do 40% of the work in 40 days and Anushka can do 1/3rd of the work in 13 days. Who will complete the work first?
Sakshi's whole work = 10 * 4 = 40 days (as 1/4 = 25% of the work)
Priyanka's whole work = 40 * (100/40) = 100 days
Anushka's whole work = 13 * 3 = 39 days
Hence Anushka will complete the given work first.


Time to Think:

A man can do a job in 15 days. His father takes 20 days to complete and his son takes 25 days to do the same. How long it takes, if they all work together?