Monday, November 5, 2018

Concept 1 - Time and Work

If A does a work in a days, then in 1 day, A does 1/a of the work.
If B does a work in a days, then in 1 day, A does 1/b of the work.
Then, in 1 day, if A and B work together, then their combined work is 1/a + 1/b = (a+b) / ab.

In the above case, we take the total work to be done as “1 unit of work”. Hence, the work will be completed when 1 unit of work is completed.

For example, if A can do a work in 10 days and B can do the same work in 12 days, then the work will be completed in how many days.
One day’s work = 1/10 + 1/12 = (12 + 10)/120 = 22/120
Then the number of days required to complete the work is 120/22.

Note that this is a reciprocal of the fraction of work done in one day. This is a benefit associated with solving time and work through fractions. It can be stated as—the number of time periods required to complete the full work will be the reciprocal of the fraction of the work done in one time period.

Alternative Approach:
Instead of taking the value of the total work as 1 unit of work, we can also look at the total work as 100 per cent work. In such a case, the following rule applies:
If A does a work in a days, then in one day A does 100/a % of the work.
If B does a work in b days, then in one day B does 100/b % of the work.
Then, in one day, if A and B work together, then their combined work is 100/a + 100/b.

This is often a very useful approach to look at the concept of time and work because thinking in terms of percentages gives a direct and clear picture of the actual quantum of work done.
What I mean to say is that even though we can think in either a percentage or a fractional value to solve the problem, there will be a thought process difference between the two.
Thinking about work done as a percentage value gives us a linear picture of the quantum of the work that has been done and the quantum of the work that is to be done. On the other hand, if we think of the work done as a fractional value, the thought process will have to be slightly longer to get a full understanding of the work done.
For instance, we can think of work done as 7/9 or 77.77%. The percentage value makes it clear as to how much quantum is left. The percentage value can be visualised on the number line, while the fractional value requires a mental inversion to fully understand the quantum.
An additional advantage of the percentage method of solving time and work problems would be the elimination of the need to perform cumbersome fraction additions involving LCMs of denominators.
However, you should realise that this would work only if you are able to handle basic percentage calculations involving standard decimal values. If you have really internalised the techniques of percentage calculations given in the chapter of percentages, then you can reap the benefits for this chapter. The benefit of using this concept will become abundantly clear by solving through percentages the same example that was solved above using fractions.

Example:

If A can do a work in 10 days and B can do the same work in 12 days, then the work will be completed in how many days.
One day’s work = 10% + 8.33% = 18.33% (Note, no LCMs required here)
Hence, to do 100% work, it will require: 100/18.33.
This can be solved by adding 18.33 mentally to get between 5–6 days. Then on you can go through options and mark the closest answer.
The process of solving through percentages will yield rich dividends if and only if you have adequate practice on adding standard percentage values. Thus, 18.33 × 5 = 91.66 should not give you any headaches and should be done while reading for the first time. 
Thus a thought process chart for this question should look like this.
If A can do a work in 10 days (Æ means 10% work) and B can do the same work in 12 days (Æ 8.33% work Æ 18.33% work in a day in 5 days 91.66% work Æ leaves 8.33% work to be done Æ which can be done in 8.33/18.33 of a day = 5/11 of a day (since both the numerator and the denominator are divisible by 1.66), then the work will be completed in 5 days. 
The entire process can be done mentally.

The Concept of Negative Work
Suppose, that A and B are working to build a wall while C is working to break the wall. In such a case, the wall is being built by A and B while it is being broken by C. Here, if we consider the work as the building of the wall, we can say that C is doing negative work.
Example: A can build a wall in 10 days and B can build it in 5 days, while C can completely destroy the wall in 20 days. If they start working at the same time, in how many days will the work be completed.
Solution: The net combined work per day here is:
A’s work + B’s work – C’s work = 10% + 20% – 5% = 25% work in one day.
Hence, the work will get completed (100% work) in 4 days.
The concept of negative work commonly appears as a problem based on pipes and cisterns, where there are inlet pipes and outlet pipes/leaks which are working against each other.
If we consider the work to be filling a tank, the inlet pipe does positive work while the outlet pipe/leak does negative work.

Application of Product Constancy Table of Time and Work
The equation that applies to Time and Work problems is
Work Rate × Time = Work done
This equation means that if the work done is constant, then Work rate is inversely proportional to time. 
Hence, the Product Constancy Table will be directly applicable to time and work questions.
[Notice the parallelism between this formula and the formula of time speed and distance, where again
there is product constancy between speed and time if the distance is constant.]
Time is usually in days or hours although any standard unit of time can be used. The unit of time that has to be used in a question is usually decided by the denominator of the unit of work rate.

Here, there are two ways of defining the Work rate.
(a) In the context of situations where individual working efficiencies or individual time requirements are given in the problem, the work rate is defined by the unit: Work done per unit time.
In this case, the total work to be done is normally considered to be 1 (if we solve through fractions) or 100% (if we solve through percentages).
Thus, in the solved problem above, when we calculated that A and B together do 18.33% work in a day, this was essentially a statement of the rate of work of A and B together.
Then the solution proceeded as:
18.33% work per day × No. of days required = 100% work
Giving us: the no. of days required = 100/18.33 = 5 (5/11).

(b) In certain types of problems (typically those involving projects that are to be completed), where a certain category of worker has the same rate of working, the Work rate will be defined as the number of workers of a particular category working on the project.
For instance, questions where all men work at a certain rate, the work rate when 2 men are working together will be double the work rate when 1 man is working alone. Similarly, the work rate when 10 men are working together will be 10 times the work rate when 1 man is working alone.
In such cases, the work to be done is taken as the number of man-days required to finish the work. Note, for future reference, that the work to be done can also be measured in terms of the volume of work defined in the context of day-to-day life. For example, the volume of a wall to be built, the number of people to be interviewed, the number of chapattis to be made and so on.

WORK EQUIVALENCE METHOD
(To Solve Time and Work Problems)
The work equivalence method is nothing but an application of the formula:
Work rate × Time = Work done (or work to be done)
Thus, if the work to be done is doubled, the product of work rate × time also has to be doubled.
Similarly, if the work to be done increases by 20%, the product of work rate × time also has to be
increased by 20% and so on.
This method is best explained by an example:
A contractor estimates that he will finish the road construction project in 100 days by employing 50 men. However, at the end of the 50th day, when as per his estimation half the work should have been completed, he finds that only 40% of his work is done.
(a) How many more days will be required to complete the work?
(b) How many more men should he employ in order to complete the work in time?
Solution:
(a) The contractor has completed 40% of the work in 50 days.
If the number of men working on the project remains constant, the rate of work also remains constant. Hence, to complete 100% work, he will have to complete the remaining 60% of the work. For this he would require 75 more days. (This calculation is done using the unitary method.)
(b) In order to complete the work on time, it is obvious that he will have to increase the number of men working on the project. This can be solved as:
50 men working for 50 days Æ 50 × 50 = 2500 man-days.
2500 man-days has resulted in 40% work completion. Hence, the total work to be done in terms of the number of man-days is got by using unitary method:
Work left = 60% = 2500 × 1.5 = 3750 man-days.
This has to be completed in 50 days. Hence, the number of men required per day is 3750/50 = 75 men. Since, 50 men are already working on the project, the contractor needs to hire 25 more men.
[Note, this can be done using the percentage change graphic for product change. Since, the number of days is constant at 50, the 50% increase in work from 40% to 60% is solely to be met by increasing the number of men. Hence, the number of men to be increased is 50% of the original number of men = 25 men.]

The Specific Case of Building a Wall (Work as volume of work)
As already mentioned, in certain cases, the unit of work can also be considered to be in terms of the
volume of work. For example, building of a wall of a certain length, breadth and height.
In such cases, the following formula applies:

where L, B and H are respectively the length, breadth and height of the wall to be built, while m, t and d are respectively the number of men, the amount of time per day and the number of days. Further, the suffix
1 is for the first work situation, while the suffix 2 is for the second work situation.
Consider the following problem:
Example: 20 men working 8 hours a day can completely build a wall of length 200 meters, breadth 10 metres and height 20 metres in 10 days. How many days will 25 men working 12 hours a day require to build a wall of length 400 meters, breadth 10 metres and height of 15 metres.
This question can be solved directly by using the formula above.
Here, 
L1 is 200 metres 
L2 is 400 metres
B1 is 10 metres 
B2 is 10 metres
H1 is 20 metres 
H2 is 15 metres
while 
m1 is 20 men 
m2 is 25 men
d1 is 10 days 
d2 is unknown
and 
t1 is 8 hours a day
t2 is 12 hours a day
Then we get (200 × 10 × 20)/(400 × 10 × 15) = (20 × 8 × 10)/(25 × 12 × d2)
d2 = 5.333/0.6666 = 8 days
Alternatively, we can also directly write the equation as follows:
d2 = 10 × (400/200) × (10/10) × (20/15) × (20/25) × (8/12)
This can be done by thinking of the problem as follows:
The number of days have to be found out in the second case. Hence, on the LHS of the equation write
down the unknown and on the RHS of the equation write down the corresponding knowns.

Then, the length of the wall has to be factored in. There are only two options for doing so. viz:
Multiplying by 200/400 (< 1, which will reduce the number of days) or multiplying by 400/200 (>1, which will increase the number of days).
The decision of which one of these is to be done is made on the basis of the fact that when the length of the wall is increasing, the number of days required will also increase.
Hence, we take the value of the fraction greater than 1 to get
d2 = 10 × (400/200)
We continue in the same way to get
No change in the breadth of the wall Æ hence, multiply by 10/10 (no change in d2)
Height of the wall is decreasing Æ hence, multiply by 15/20 (< 1 to reduce d2)
Number of men working is increasing Æ hence, multiply by 20/25 (< 1 to reduce d2)
Number of hours per day is increasing Æ hence, multiply by 8/12 (< 1 to reduce the number of days)

The Concept of Efficiency
The concept of efficiency is closely related to the concept of work rate.
When we make a statement saying A is twice as efficient as B, we mean to say that A does twice the work as B in the same time. In other words, we can also understand this as A will require half the time required by B to do the same work.
In the context of efficiency, another statement that you might come across is A is two times more efficient than B. This is the same as A is thrice as efficient as B or A does the same work as B in 1/3rd of the time.
Equating Men, Women and Children This is directly derived from the concept of efficiencies.
Example: 8 men can do a work in 12 days while 20 women can do it in 10 days. In how many days can 12 men and 15 women complete the same work.
Solution: Total work to be done = 8 × 12 = 96 man-days.
or total work to be done = 20 × 10 = 200 woman-days.
Since, the work is the same, we can equate 96 man-days = 200 woman-days.
Hence, 1 man-day = 2.08333 woman-days.
Now, if 12 men and 15 women are working on the work we get
12 men are equal to 12 × 2.08333 = 25 women
Hence, the work done per day is equivalent to 25 + 15 women working per day.
That is, 40 women working per day.
Hence, 40 × no. of days = 200 woman days
Number of days = 5 days. 

1 comment: